Project profitability

A project looks healthy until the final account.

Compare budget with actual cost, find the variance and run a delay.

Demo on fictional data — never customer data.

Pick an open project. A delay recalculates expected final cost from booked labour per week.

Budget
€185,000
Actual
€141,700
Progress
65.0%
Expected final cost
€218,000
Expected margin
14.8%
Target margin
30.0%
Delay

135 hours above earned hours. Material price is €30 above budget. A 0-week delay adds €0.

DAX
Verwachte eindkosten =
DIVIDE ( [Werkelijke kosten], [Voortgang] )

Verwachte marge =
DIVIDE (
    [Contractwaarde] - [Verwachte eindkosten],
    [Contractwaarde]
)

EAC = actual cost / progress · €218,000